Why Big Tech is buying nuclear power plants
Microsoft, Google, Amazon and Meta have signed close to 10 gigawatts of nuclear deals. A nuclear engineer explains why they want nuclear, which deals will actually deliver power soon, and which are long shots.
Plain-English explainer by Joe Miller, a nuclear engineer. Not investment advice. Figures are the latest public numbers we could find and change fast; sources are at the bottom of each page.
Why AI companies want nuclear
- It runs all the time. A data center needs power 24 hours a day, 365 days a year. Nuclear plants run more than 90% of the time, more than any other source.
- It doesn't emit carbon, which matters to companies that promised to cut emissions.
- It's compact. A 1,000-megawatt reactor fits on a site of about a square mile; the same output from solar takes thousands of acres plus batteries.
- Grid power is getting scarce and expensive where data centers want to build (see your electric bill).
Three ways to get it
The deals, and when the power could arrive
| Company | Partner and plant | Type | Size | Target date |
|---|---|---|---|---|
| Microsoft | Constellation, Three Mile Island Unit 1 (renamed Crane), Pennsylvania | Restart; 20-year, about $16 billion deal | 835 MW | 2027 |
| NextEra, Duane Arnold, Iowa | Restart; 25-year deal; $1.9 billion federal loan (Sept. 2026) | 615 MW | Early 2029 | |
| Kairos Power | New small reactors (molten-salt cooled) | 500 MW | 2030 to 2035 | |
| Meta | Vistra: Perry and Davis-Besse (Ohio), Beaver Valley (Pennsylvania) | Existing output plus uprates; 20-year deals | about 2,600 MW | Late 2026 to 2034 |
| Meta | Oklo, Pike County, Ohio | New small reactors (75 MW units) | up to 1,200 MW | First phase about 2030 |
| Meta | TerraPower | Up to 8 Natrium sodium-cooled reactors | about 2,800 MW | 2032 to 2035 |
| Meta | Constellation, Clinton, Illinois | Existing plant; 20-year deal | plant output | Underway |
| Amazon | X-energy and Energy Northwest, Washington State | New small reactors; $700 million investment in X-energy | 320 MW first phase, up to 960 MW | 2030s |
| Amazon | Talen Energy, Susquehanna, Pennsylvania | Existing plant | large share of plant output | Underway |
All four companies signed at least one nuclear deal in 2026; together they total close to 10 gigawatts, by Forbes' count.
My take: what's real and what's hype
Real and soon: the restarts and the deals for power from running plants. Crane and Duane Arnold are physical plants with trained staff, a fuel supply chain and a regulator that knows them. Barring surprises, they'll add power this decade. Michigan's Palisades plant, which began loading fuel in September 2026 to restart without a Big Tech buyer, is the test case everyone is watching.
Real, but slower than the press releases: the small modular reactors. The physics is sound, and some designs build on decades of research. But none of these designs is running commercially in the U.S. yet. First-of-a-kind plants almost always run late and over budget. Vogtle 3 and 4 in Georgia, the last big reactors built in the U.S., finished about seven years late and billions over budget. Expect 2030 to 2035 at the earliest for meaningful amounts.
The catch with buying from existing plants: when a tech company buys power from a plant that's already running, that power stops serving everyone else. Regulators and other customers have pushed back on some of these deals for exactly that reason.
What it means for you
- New nuclear jobs and tax base near Crane, Duane Arnold, Ohio and Washington State.
- Electric bills: if tech companies pay for new power, that can ease pressure on the grid. If they lock up existing power, the rest of us compete for what's left.
- Nuclear's comeback is real. After decades of plant closures, the U.S. is restarting plants and planning new ones. The U.S. Department of Energy pledged up to $17.5 billion in loans in June 2026 for 10 new large reactors.
Sources
Checked November 16, 2026.
- Forbes: The AI boom is making nuclear power bankable again (July 26, 2026)
- World Nuclear News: Constellation seeks regulator's help for 2027 plant restart (April 1, 2026)
- Canary Media: Shuttered Iowa nuclear plant gets $1.9B federal loan to restart (Sept. 8, 2026)
- Introl: Meta's 6.6 GW nuclear deals with Vistra, TerraPower and Oklo (Jan. 2026)
- SMR Intel: Every nuclear-powered data center deal (updated July 2026)