Microsoft, Google, Amazon and Meta have signed close to 10 gigawatts of nuclear deals. A nuclear engineer explains why they want nuclear, which deals will actually deliver power soon, and which are long shots.

Why nuclearThree pathsThe dealsReal or hypeWhat it means for youSources

Plain-English explainer by Joe Miller, a nuclear engineer. Not investment advice. Figures are the latest public numbers we could find and change fast; sources are at the bottom of each page.

Why AI companies want nuclear

Three ways to get it

Three ways to get nuclear power for AIRestart a closed plantFastest: about 2 to 4 yearsPlant already built and licensedonceOnly a handful left to restartExample: Three Mile Island Unit 1Buy from running plantsPower on day oneUprates add 5 to 20% moreCritics: it shifts existing poweraway from everyone elseExample: Meta and VistraBuild new reactorsBig reactors: about 10 years andbillions (Vogtle)Small modular reactors: promising,unproven at scaleEarliest new units around 2030Examples: Kairos, X-energy, Oklo,TerraPower
Restarts are fastest; new reactors take the longest.

The deals, and when the power could arrive

Big Tech's nuclear bets: when the power could arrive (company targets)202620282030203220342036Meta + VistraExisting plants + uprates, OH and PA · about 2,600 MWMicrosoft + ConstellationRestart: Three Mile Island Unit 1 (Crane) · 835 MWGoogle + NextEraRestart: Duane Arnold, Iowa · 615 MWMeta + OkloNew small reactors, Pike County, OH · up to 1,200 MWGoogle + KairosNew small reactors · 500 MWAmazon + X-energyNew small reactors, Washington State · 320 MW first, up to 960Meta + TerraPowerUp to 8 Natrium reactors · about 2,800 MWExisting or restarted plants: sooner, surerNew designs: none yet running commercially in the U.S.
Dates are the companies' own targets and often slip.
CompanyPartner and plantTypeSizeTarget date
MicrosoftConstellation, Three Mile Island Unit 1 (renamed Crane), PennsylvaniaRestart; 20-year, about $16 billion deal835 MW2027
GoogleNextEra, Duane Arnold, IowaRestart; 25-year deal; $1.9 billion federal loan (Sept. 2026)615 MWEarly 2029
GoogleKairos PowerNew small reactors (molten-salt cooled)500 MW2030 to 2035
MetaVistra: Perry and Davis-Besse (Ohio), Beaver Valley (Pennsylvania)Existing output plus uprates; 20-year dealsabout 2,600 MWLate 2026 to 2034
MetaOklo, Pike County, OhioNew small reactors (75 MW units)up to 1,200 MWFirst phase about 2030
MetaTerraPowerUp to 8 Natrium sodium-cooled reactorsabout 2,800 MW2032 to 2035
MetaConstellation, Clinton, IllinoisExisting plant; 20-year dealplant outputUnderway
AmazonX-energy and Energy Northwest, Washington StateNew small reactors; $700 million investment in X-energy320 MW first phase, up to 960 MW2030s
AmazonTalen Energy, Susquehanna, PennsylvaniaExisting plantlarge share of plant outputUnderway

All four companies signed at least one nuclear deal in 2026; together they total close to 10 gigawatts, by Forbes' count.

My take: what's real and what's hype

Real and soon: the restarts and the deals for power from running plants. Crane and Duane Arnold are physical plants with trained staff, a fuel supply chain and a regulator that knows them. Barring surprises, they'll add power this decade. Michigan's Palisades plant, which began loading fuel in September 2026 to restart without a Big Tech buyer, is the test case everyone is watching.

Real, but slower than the press releases: the small modular reactors. The physics is sound, and some designs build on decades of research. But none of these designs is running commercially in the U.S. yet. First-of-a-kind plants almost always run late and over budget. Vogtle 3 and 4 in Georgia, the last big reactors built in the U.S., finished about seven years late and billions over budget. Expect 2030 to 2035 at the earliest for meaningful amounts.

The catch with buying from existing plants: when a tech company buys power from a plant that's already running, that power stops serving everyone else. Regulators and other customers have pushed back on some of these deals for exactly that reason.

What it means for you

Sources